Major Projects
Drilling, Testing & Fracturing Projects
PROJECT DETAILS COMPLETION
Drilling Services in Indus Basin – Total Wells Drilled 105 ( Average depth 3500 meter and maximum depth upto 5500 meters) Ongoing Contract
Well Testing Services in Indus Basin, Cambay Basin Mar 2004-Till date
Seismic Services - 2D and 3D Services in Indus Basin Feb 2008
Marine Seismic Services for Focus Energy, Indus Gas Limited in Cambay basin Feb 2013 to Till date
Data Processing & Interpretation for both 2D and 3D Continuing Contract
Cased Hole Logging and DST Services for Focus Energy, Indus Gas Limited Continuing Contract
Gradient Survey, PVT Sampling, Gas Sampling Continuing Contract
Fracturing Services in Indus Basin, Cambay Basin – Upto 15000 psig pressure Sep 2010 – Till date

 

Oil & Gas Engineering, Fabrication, Electrical Projects
PROJECT DETAILS COMPLETION
90 KM 6” 1500 psig Natural Gas Pipeline Jan 2009
120 Kms of 4” 3000 psig Natural Gas Well Line connecting wellhead to process plants (Total 11 wells connected) Jan 2009 to March 2013 (over period of time)
15 MMSCFD Gas Processing plant Design, Engineering & Fabrication Consisting of Separators, Filter Separators, 4 GPM TEG Dehydration Unit Sep 2008-Jan 2009
Erection , Installation & Commissioning of 15 MMSCFD Gas Processing Plant Jun 2009
65 MMSCFD Gas Processing plant Design, Engineering & Fabrication Consisting of Separators, Filter Separators, 1800 GPM Amine Plant, 14 GPM TEG Dehydration Unit Feb-2012 to March 2012
Erection , Installation & Commissioning of 65 MMSCFD Gas Processing Plant Sep 2012
Design, Supply, Erection, Testing & Commissioning of 11KV Sub Station including Step down Transformers 11/3.3 KV and 11KV/415V, Electrical Panels, Capacitor Bank, Bus Bar Panels, and NGR/NIS Panels Sep 2012
Design, Supply, Erection, Testing & Commissioning of ABB SCADA System Sep 2012
Design, Supply, Erection, Testing & Commissioning of 2 x 9.5 million calorie Thermic Fluid Heaters Sep 2012